CO129-335 - Governor Nathan - 1906 [8-10] — Page 367

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

(O.C.P.Y.)

No.

Enclosure 2 to Confidential despatch of 16th November 1909

Your Excellency,

41029

363

RECD. Hong Kong!

NOV 06

Four causes are specified in the Chief Resident Engineer's letter for the unsatisfactory progress made with the work. They are:-

(a). Exorbitant prices charged by local contractors.

(b). Sickness.

(c). Poor quality of labour.

(d). Insufficient plant.

The C.R.E. states (para. 2) that Contractors cannot be persuaded to start work during May to October.

In the case of the "City Water Works Extension" referred to in my Notes of the 12.9.08, the Contract (amount $495,000 or, say, £50,000) was signed on the 13th March, 1904. Temporary quarters for the men and sheds for storing materials had to be erected and consequently none of the actual work was begun until some weeks later. The following is a statement of the number of men employed on the work during the months referred to by the C.R.E:-

Month | Average daily number | Rainfall inches

May | 565 | 7.70

June | 444 | 19.64

July | 684 | 7.22

August | 503 | 27.34

Sept. | 489 | 9.77

Good progress was made with the work during the period referred to, though sickness was very prevalent.

In the case of the Kowloon Water Works, which are situated in the locality of the Tunnel Works, the principal Contract ($608,700 = say, £52,000) was signed on the 20th May, 1909. Fair progress was made with the work during the ensuing months.


Page 363

(the last three lines are kept as is, assuming they are part of the page numbering)

No reordering or additional text is added as per the instructions. The text is formatted into paragraphs and a table using HTML. Spelling errors are corrected, and spacing issues are fixed. The original text's content and structure are preserved as much as possible.

Edit History

2026-06-02 09:28:19 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
(O.C.P.Y.) No. Enclosure 2 to Confidential despatch of 16th November 1909 Your Excellency, 41029 363 RECD. Hong Kong! NOV 06 Four causes are specified in the Chief Resident Engineer's letter for the unsatisfactory progress made with the work. They are:- (a). Exorbitant prices charged by local contractors. (b). Sickness. (c). Poor quality of labour. (d). Insufficient plant. The C.R.E. states (para. 2) that Contractors cannot be persuaded to start work during May to October. In the case of the "City Water Works Extension" referred to in my Notes of the 12.9.08, the Contract (amount $495,000 or, say, £50,000) was signed on the 13th March, 1904. Temporary quarters for the men and sheds for storing materials had to be erected and consequently none of the actual work was begun until some weeks later. The following is a statement of the number of men employed on the work during the months referred to by the C.R.E:- Month | Average daily number | Rainfall inches May | 565 | 7.70 June | 444 | 19.64 July | 684 | 7.22 August | 503 | 27.34 Sept. | 489 | 9.77 Good progress was made with the work during the period referred to, though sickness was very prevalent. In the case of the Kowloon Water Works, which are situated in the locality of the Tunnel Works, the principal Contract ($608,700 = say, £52,000) was signed on the 20th May, 1909. Fair progress was made with the work during the ensuing months. Page 363 (the last three lines are kept as is, assuming they are part of the page numbering) No reordering or additional text is added as per the instructions. The text is formatted into paragraphs and a table using HTML. Spelling errors are corrected, and spacing issues are fixed. The original text's content and structure are preserved as much as possible.
Baseline (Original)
(0 0 P Y) No. Enclomere 2 to Confidential auspatele of flipto Your Excellency, 41029 363 RECH Ring! NOV 06 four causes are specified in the Chief Resident Engineer's letter for the unsatisfactory orogress made with the Exorbitant prices charged by local con- work. They are:- (E). Sickness. (b). Poor ouality of labour. (c). (a). (a) Sickness. tractors. Insufficient piens. the C.k.b. states (oara. 2) that Contractors cannot be persuaded to start work during Vay to October, 5 In the case of the "City later horks Extensior " referred to in my Notes of the 12.9.08, the Contract, (amount $495,000 or, say, 850,000), was signed on the 13th, March, 1904. Tenoorary quarters for the men and sheds for storing meterials had to be erected and consecuently rone of the sctuel work was begun until some reeks later. The following is a statement of the number of mea employed on the work during the months referred to by the 0.8.B.I- Fsinfall inches Way June average daily number 565 7.70 444 19.64 July 684 7.22 August 503 27.34 Seotr. 489 9.77 Good progress was made with the work during the period referred to though sickness vcs very orev al ent. In the case of the Kowloos Water Works, which are situated in the locality of the Tunnel Works, the orincipal Contract ($608,700 = say, f52,000) was signed on the 20th. Mey, 1909 Feir oro- dress was made with the work during the ensuing months, O the
2026-06-02 09:28:19 · Baseline
View content

(0 0 P Y)

No.

Enclomere 2 to Confidential auspatele of flipto

Your Excellency,

41029

363

RECH Ring!

NOV 06

four causes are specified in the Chief Resident

Engineer's letter for the unsatisfactory orogress made with the

Exorbitant prices charged by local con-

work. They are:-

(E).

Sickness.

(b).

Poor ouality of labour.

(c).

(a).

(a)

Sickness.

tractors.

Insufficient piens.

the C.k.b. states (oara. 2) that Contractors cannot

be persuaded to start work during Vay to October,

5

In the case of the "City later horks Extensior "

referred to in my Notes of the 12.9.08, the Contract, (amount

$495,000 or, say, 850,000), was signed on the 13th, March, 1904.

Tenoorary quarters for the men and sheds for storing meterials had to

be erected and consecuently rone of the sctuel work was begun until

some reeks later. The following is a statement of the number of mea

employed on the work during the months referred to by the 0.8.B.I-

Fsinfall inches

Way

June

average daily number 565

7.70

444

19.64

July

684

7.22

August

503

27.34

Seotr.

489

9.77

Good progress was made with the work during the

period referred to though sickness vcs very orev al ent.

In the case of the Kowloos Water Works, which are situated in the locality of the Tunnel Works, the orincipal Contract ($608,700 = say, f52,000) was signed on the 20th. Mey, 1909 Feir oro-

dress was made with the work during the ensuing months,

O

the

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.